Use the Earned Value Management (EVM) Calculator to measure project performance by comparing planned progress, actual costs, and earned value.
Formula (plain text):
CPI = EV / AC SPI = EV / PV EAC = AC + BAC – EV SV = EV – PV
Note: BAC = Budget at Completion, EV = Earned Value, AC = Actual Cost, PV = Planned Value.
Formula Overview
Planned Value (PV) = BAC × (% Planned Complete)
Earned Value (EV) = BAC × (% Actual Complete)
Cost Performance Index (CPI) = EV ÷ AC
Schedule Performance Index (SPI) = EV ÷ PV
Estimate at Completion (EAC) varies by method:
EAC₁ = AC + (BAC − EV) ÷ CPI
EAC₂ = AC + (BAC − EV) ÷ (CPI × SPI)
EAC₃ = AC + BAC − EV
Variance Calculations
Cost Variance (CV) = EV − AC
Schedule Variance (SV) = EV − PV
Example
BAC = 100,000
Planned Complete = 50%
Actual Complete = 40%
Actual Cost (AC) = 45,000
Results:
PV = 50,000
EV = 40,000
CPI = 0.89
SPI = 0.8
SV = −10,000
EAC (Method 3) = 105,000
The project is slightly behind schedule and over budget, requiring corrective actions.
Metric Abbrev. Formula / Basis Value Meaning Budget at Completion BAC Total planned project budget $100,000 Total approved budget for project completion Planned Value PV BAC × (% Planned Complete) $50,000 Budgeted cost of work scheduled Earned Value EV BAC × (% Actual Complete) $40,000 Budgeted cost of work actually completed Actual Cost AC User input $45,000 Actual cost incurred for work performed Schedule Variance SV EV − PV −$10,000 Negative → project is behind schedule Cost Variance CV EV − AC −$5,000 Negative → project is over budget Cost Performance Index CPI EV ÷ AC 0.89 < 1 → cost inefficient Schedule Performance Index SPI EV ÷ PV 0.80 < 1 → behind schedule Estimate at Completion EAC AC + BAC − EV $105,000 Forecast total project cost Estimate to Complete ETC EAC − AC $60,000 Expected remaining cost Variance at Completion VAC BAC − EAC −$5,000 Negative → likely cost overrun Performance Rating — Composite (e.g., CPI × SPI) 0.9 Watch Overall health slightly below target